Construction update

Union Green Construction Update

The team at Myland Partners and Dominon are pleased to report that significant progress has been made at Union Green since May 2019.

Progress has been increased steadily over the past few months, Dominion now has teams throughout all four blocks, working on the internal and external areas at the same time.

Progress by block:

The North Terraces have had the roof installed with window and wall linings currently being completed. The building is now watertight and advanced to internal door installation and gib boarding to all walls.

The West Terraces have had the roof installed with window and wall linings currently being completed. The timber stairs have been installed and all timber floors are now completed

The Central Terraces have had the roof installed with services installation continuing

The Rise’s lift tower has been completed as well as the structural floors up to level eight. Services and fitout is continuing in the lower levels.

Completion Dates

Together, Dominion and Myland Partners are focused on delivering this iconic project within the revised time frames to a standard we can all be proud of.

The updated completion dates with Dominion are projected as follows:

The Terraces (North, West, Central) – January 2020

The Rise (Apartments & Green Terraces) – May 2020